Grace Street Utility Project Pictures

1/26/21 - Equipment/Materials onsite

January 26, 2021 January 26, 2021

1/29/21 - Grace Street from Institue to North Church is Closed

2/1/21 - Digging underway

2/4/21- Sewer line work progressing down Grace Street

 

2/5/21 - Sewer work progressing down Grace Street

  

2/8/21 - Sewer work progressing along Grace Street

 

2/12/21 - Manhole #2 set

 

2/15/21 - Continued work on Grace Street

 

2/26/21 - Sewer man hole #6 set

 

3/10/21 - Sewer work progressing on Mason Street

3/12/21 - Work continuing on Mason Street South of Grace Street

 

3/22/21 - Sewer laterals being installed

 

4/13/21 - Sewer work nearing completion

 

 

 

4/14/21 - Laying out water line route

 

4/21/21 - Installation of new 8" water main begins bear Thomas St. and N. Church Street

 

4/27/21 - 8" water main is now installed from North Church to Institute.  The valve group has been installed at the intersection of Grace and Institute.

5/14/21 - Water main and fire hydrant installation.

 

 

6/23/21

Water service connections being made down Grace Street

 

 

10/8/21 - Sewer is installed from Cary to Main.  Work is underway on the Water main installation.

 

 

 